Private Investment in Transport Infrastructure: Dealing with Uncertainty in Contracts
Research Report, Policy Insights,
21 June 2018
- Pursue private investment in infrastructure on the merits of improved efficiency.
- Invest more into upfront preparation of projects to reduce inefficient risk pricing by suppliers.
- Undertake a comprehensive analysis of how to assist suppliers.
- The pursuit of certainty in delivery should be balanced against cost.
- Stimulate innovation through early contractor involvement or alliancing, not public-private partnerships.
- Avoid transferring demand risk to public-private partnerships if service levels do not strongly impact demand.
- Bundle and cross-fund public-private partnerships to reduce demand risk.
- Adopt the regulatory asset base model where competition is absent or demand not strongly endogenous.
- Introduce a transparent public accounting standard to maximise the value for money of private investment.
- Foster competitive markets to achieve cost-effective infrastructure.
- Pursue data collection on how contract design affects project outcomes.
- Support the development of an evidence-supported procurement tool.
Integrating Urban Public Transport Systems and Cycling
Roundtable Report, Policy Insights,
25 April 2018
- Design interchange stations to provide secure, uncongested conditions for transfer by the shortest routes possible.
- Provide adequate bike parking areas at stations and stops.
- Integrate ticketing and information systems as well as the physical transport infrastructure.
- Establish integrated urban transport plans in consultation with stakeholders and the public.
Partenariats public-privé pour les infrastructures de transport
Roundtable Report, Policy Insights,
29 January 2018
- Ne renégocier les PPP que dans des cas exceptionnels.
- Faire appel à un arbitre indépendant pour établir si le résultat d’un PPP cadre avec ce que les parties auraient négocié si elles avaient prévu le changement intervenu.
- Envisager de charger une instance indépendante de statuer sur le bien-fondé de la renégociation d’un PPP.
- Inclure la réputation et la compétence avérée parmi les critères d’attribution des contrats de PPP.
- Comparer les avantages et inconvénients des PPP avec ceux des autres formes de participation des capitaux privés.
Adapting Transport to Climate Change and Extreme Weather
Research Report, Policy Insights,
14 December 2016
- Act now to preserve the value of transport infrastructure and maintain network performance.
- Protect transport infrastructure against climate impacts through good maintenance.
- Prepare for more frequent and unexpected failure of transport infrastructure.
- Account for temporary unavailability of transport assets in in service continuity plans.
- Assess vulnerability of transport assets and networks from climate change and extreme weather.
- Focus on transport system resilience, not just on designing robust infrastructure.
- Re-evaluate thinking on redundant transport infrastructure.
- Do not rely solely on cost-benefit analysis for appraising the value of transport infrastructure.
- Develop new decision-support tools that incorporate deep uncertainty into asset appraisal.
Capacity to Grow: Transport Infrastructure Needs for Future Trade Growth
Corporate Partnership Board Report, Policy Insights,
8 May 2016
- Develop planning tools to adapt to uncertainties: Good port planning means planning for uncertainties.
- Increase port capacity by optimising existing terminals.
- Take a holistic planning approach to improving port capacity needs as part of the entire supply chain.
- Use funding as a balancing tool in port capacity development.
Better Regulation of Public-Private Partnerships for Transport Infrastructure
Roundtable Report, Policy Insights,
24 September 2013
- A mix of financing models spreads risks.
- A dedicated budget for PPPs, set in relation to the rate at which future liabilities will be accumulated, can provide such a limit.
- Explicit consideration of alternative financing arrangements should be employed in determining whether to proceed with PPP projects.
- It is recommended that governments require PPP projects to pass tests of affordability and to clear the hurdle rates of return generally applied to publicly financed transport projects.
- The expected cost of PPP projects should take account of cost inflation resulting from the propensity for projects to be renegotiated.
- At the individual project level, risks should be assigned to the party best able to manage them, along with rights to make related decisions.
- Assigning demand risk is not straightforward and risk sharing arrangements are therefore common.
- Continuity of resources and expertise is essential for addressing strategic behaviour and optimism bias more generally.
- Regulatory agencies are well placed to ensure transparency and accountability by publishing reports on the criteria employed to make decisions and publishing contracts.